Anderson Park District lists a Clear Creek Park bike park in the design phase, with completion expected in 2027, in its November capital-project update.
The district’s Nov. 10 status matrix also identifies construction at Laverty Park and W. M. Johnson Hills Park. The timetable notes that some expected completion dates have been revised for planning and construction delays.
Laverty’s work includes a restroom unit and parking-lot renovation. Johnson Hills’ project renovates natural-surface trails.
The district’s Laverty project description says the upgrades add flush toilets, maintenance storage, accessibility improvements, fencing and parking-lot resurfacing.
Riverside Park’s conversion of ballfield infields to an all-weather surface is marked complete in the November matrix.
The projects are part of improvements supported by the capital levy voters approved in November 2023. The district posts its project list and progress reports on its website.